San Bernardino's 65% Construction Debris Diversion Rule, Explained
If you're pulling a building permit in San Bernardino, 65% of your debris has to be diverted from landfill - with paperwork to prove it. Here's how that works.

In this guide
- The rule that surprises people
- Where the 65% comes from
- The Waste Management Plan
- What counts as diversion
- How to actually hit the target
- Documentation the City wants
- Where a local hauler fits
- The bottom line
Most guides to renting a dumpster talk about size and price. In San Bernardino there is a more consequential question for anyone pulling a building permit: how are you going to divert 65 percent of your debris from landfill, and can you prove it? Get that wrong and your permit sign-off stalls.
The rule that surprises people
Homeowners and contractors new to a permitted project in San Bernardino are often caught off guard by it. You cannot simply fill a container, send it to a landfill and be done. The City requires that most of your construction and demolition debris be recycled or reused rather than buried, and it requires documented proof.
This is not a San Bernardino quirk so much as California law applied locally, but the City administers it with specific requirements, and the responsibility for compliance lands on the permit holder.
Where the 65% comes from
California's CALGreen building code requires that at least 65 percent of construction and demolition materials be diverted from landfill through recycling or reuse. The City of San Bernardino implements this through its own Construction and Demolition Recycling Program under the municipal code.
The requirement applies to covered projects - typically new construction, additions, alterations and renovations that require a building permit and are not specifically exempt. Work needing only a plumbing, electrical or mechanical permit is generally outside it, as are some small projects, but the threshold catches most real renovation and construction work.
The Waste Management Plan
The mechanism is a document called a Waste Management Plan, or WMP. You submit it to the City's Public Works Department along with your building permit application, before the project starts.
The plan estimates how much debris the project will generate, broken down by material type, and describes how each stream will be diverted - which materials go to recycling, which are reused, and which unavoidably go to landfill. It sets an anticipated diversion rate that has to meet the 65 percent threshold.
At the end of the project you submit the proof: weight receipts from the facilities, hauler diversion reports, and any reuse documentation, showing you actually achieved what the plan promised. Fall short on the documentation and you can forfeit a diversion deposit and delay your final sign-off.
What counts as diversion
Diversion means the material did not go into a landfill. In practice that means recycling or reuse.
The easy wins are the heavy, cleanly separable streams. Clean concrete, block and asphalt can be crushed into base material. Clean wood can be chipped. Metal is recycled and has scrap value. Cardboard and clean green waste are both readily diverted. Drywall can often be recycled at the right facility.
The enemy of diversion is mixing. A container of thoroughly mixed debris is hard to divert and often gets counted as disposal. A set of reasonably separated streams diverts easily. So the single most useful habit on a San Bernardino job is keeping your clean concrete, metal, wood and cardboard out of the general trash container.
How to actually hit the target
Sixty-five percent sounds daunting until you look at the weights. On most construction and demolition projects, the heavy materials - concrete, masonry, dirt - dominate the tonnage. Divert those cleanly and you are most of the way to the target before you have touched the light debris.
So the strategy is straightforward: run a dedicated container for clean concrete and heavy inert material routed to a recycler, separate your metal and cardboard, keep green waste clean for composting, and let the general container take only what genuinely cannot be diverted. Done that way, 65 percent is very achievable.
Documentation the City wants
The paperwork is where projects stumble, because it has to be gathered as you go rather than reconstructed at the end. Keep every scale ticket and weight receipt from every facility. Keep the recycler's documentation showing what was diverted. If you reused material on site, document that too.
Using a hauler that routes to permitted recycling facilities and provides those receipts as a matter of course removes most of the pain. The alternative - chasing paperwork across several facilities after the fact - is exactly the scramble the deposit is designed to punish.
Where a local hauler fits
This is where working with a company that knows the San Bernardino system earns its keep. We route your debris to permitted recycling and disposal facilities that document the diversion, we run a tarped truck, and we provide the weight receipts and diversion records your Waste Management Plan requires.
We cannot file your WMP for you - that is the permit holder's document - but we can make the diversion side of it work in practice, which is the part most projects find hardest. If you tell us it is a covered project, we set up the container mix that hits the target rather than leaving you to discover the shortfall at closeout.
The bottom line
On any permitted construction or demolition project in San Bernardino, plan for the 65 percent diversion requirement from the start. File a Waste Management Plan with Public Works, separate your heavy and recyclable streams, keep every receipt, and use a hauler who routes to permitted recyclers and documents it. Handled that way it is routine. Ignored until closeout, it is a delayed permit and a forfeited deposit.
Book a container in San Bernardino
One flat rate covering delivery, seven days, pickup and disposal.
(909) 361-3356Questions readers ask about this
What is the 65% diversion requirement in San Bernardino?
Under California's CALGreen code and the City's own program, at least 65 percent of construction and demolition debris from a covered permitted project must be diverted from landfill through recycling or reuse, documented in a Waste Management Plan.
What is a Waste Management Plan?
A document submitted to the City's Public Works Department with your building permit that estimates the debris your project will generate and describes how 65 percent of it will be diverted from landfill. You document the actual diversion with receipts at project end.
How do I actually hit 65% diversion?
Separate your streams. Clean concrete and masonry, metal, wood, cardboard and green waste all divert readily and the heavy materials dominate the tonnage, so diverting those cleanly gets you most of the way. We set up the container mix to make it work.
What happens if I don't document the diversion?
You can forfeit a diversion deposit and delay your final permit sign-off. The documentation - weight receipts and diversion reports - has to be gathered as you go, which is why a hauler that provides those receipts helps.